Jundi Electrical Industry part of TECO Group won the supply of all LV Electrical panels for Ministry Finance Complex with Derar Saraireh & Sons for Engineering & Contracting
Project Consultant: AL BAHA ENGINEERING CONSULTANTS
Supply of All Distribution Boards
- Main Distribution Boards Form 4
- Sub-main Distribution Boards Form 2
- Motor Control Centers
- Final Distribution Boards
- Automatic Power Factor Correction Panel
First batch of Panels were ready for delivery on 23-01-2019
Second batch of Panels were ready for delivery on 21-04-2019
Third batch of Panels were ready for delivery on 31-07-2019. Click here to read more
Fourth batch of Panels were ready for delivery on 20.10.2019. Click here to read more
Fifth batch of Panels were ready for delivery on 31.01.2021. Click here to read more